Answers
-
HeatherD。 Moderator
Hi@KCrownover,
If you use the Resource Management Panel in Smartsheet, you can definitely do this! Here is a brief outline of how it could work:
- Import the data from your old system into Smartsheet
- For more information on how to do this, seeImport Files to Create New Sheets.
- If you need to copy rows from your imported sheet into an existing Project sheet, seeCopy rows to another sheet.
- When building your project sheet, you'll want to be sure that these 5 columns are populated for all rows that you want to sync:
- Primary Column (usually the task name)
- Start Date
- End Date
- Assigned To
- Allocation %
- In project settings, enable dependencies and turn on Resource Management, then select the Allocation % column.
- Use the Resource Management button from the right menu bar to access the Resource Management Panel. You'll want to follow the steps inAbout the Resource Management Panelto ensure your connection is made correctly.
- You'll be able to either select an existing project in Resource Management, or create a new one from the project in Smartsheet.
I hope this helps! If you have any difficulty with the connection,Troubleshoot Resource Management panel connectionmay be a helpful resource to you.
Best,
Heather
- Import the data from your old system into Smartsheet
Categories
Create a field that checks if both the created date is more then 3 days ago and the status is \"Not Started\". Then have an automation run every morning that is filtered to this field being checked.<\/p>
Example formula:<\/p>
=IF(AND(Status@row=\"Not Started\",(TODAY()-[Created Date]@row)>3),1,0)<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":355,"name":"Resource Management","url":"https:\/\/community.smartsheet.com\/categories\/resource-management","allowedDiscussionTypes":["discussion","question"]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[]},{"discussionID":108074,"type":"question","name":"Stop people from tracking to a project when an hours or fee budget is exhausted","excerpt":"Hi Community! Does anyone know if there is a way to set up a project in Resource Management so when the time or fee budget is exhausted, people can no longer track time to that project? The only lock setting I am able to see if one to lock time entries to the project once added (or after 14 days). Not sure if I am just…","snippet":"Hi Community! Does anyone know if there is a way to set up a project in Resource Management so when the time or fee budget is exhausted, people can no longer track time to that…","categoryID":355,"dateInserted":"2023-07-25T23:15:36+00:00","dateUpdated":null,"dateLastComment":"2023-07-27T23:41:37+00:00","insertUserID":163801,"insertUser":{"userID":163801,"name":"beverlyjosie","title":"Governance and Operations Coordinator","url":"https:\/\/community.smartsheet.com\/profile\/beverlyjosie","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-08-01T18:14:14+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"updateUserID":null,"lastUserID":8888,"lastUser":{"userID":8888,"name":"Andrée Starå","title":"Smartsheet Expert Consultant & Partner | Workflow Consultant \/ CEO @ WORK BOLD","url":"https:\/\/community.smartsheet.com\/profile\/Andr%C3%A9e%20Star%C3%A5","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/0PAU3GBYQLBT\/nXWM7QXGD6464.jpg","dateLastActive":"2023-08-26T00:32:09+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":5,"countViews":128,"score":null,"hot":3380831233,"url":"https:\/\/community.smartsheet.com\/discussion\/108074\/stop-people-from-tracking-to-a-project-when-an-hours-or-fee-budget-is-exhausted","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/108074\/stop-people-from-tracking-to-a-project-when-an-hours-or-fee-budget-is-exhausted","format":"Rich","tagIDs":[468],"lastPost":{"discussionID":108074,"commentID":387700,"name":"Re: Stop people from tracking to a project when an hours or fee budget is exhausted","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/387700#Comment_387700","dateInserted":"2023-07-27T23:41:37+00:00","insertUserID":8888,"insertUser":{"userID":8888,"name":"Andrée Starå","title":"Smartsheet Expert Consultant & Partner | Workflow Consultant \/ CEO @ WORK BOLD","url":"https:\/\/community.smartsheet.com\/profile\/Andr%C3%A9e%20Star%C3%A5","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/0PAU3GBYQLBT\/nXWM7QXGD6464.jpg","dateLastActive":"2023-08-26T00:32:09+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Get Help","url":"https:\/\/community.smartsheet.com\/categories\/get-help"},{"name":"Resource Management","url":"https:\/\/community.smartsheet.com\/categories\/resource-management"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2023-07-26T16:36:54+00:00","dateAnswered":"2023-07-26T16:13:19+00:00","acceptedAnswers":[{"commentID":387210,"body":"
I hope you're well and safe!<\/p>
Unfortunately, as far as I know, it's not possible now, but it's an excellent idea!<\/p>
Be safe, and have a fantastic week!<\/p>
Andrée Starå<\/strong><\/a> | Workflow Consultant \/ CEO @ WORK BOLD<\/strong><\/a><\/p>
Hi @Nkeiruka. Aguocha<\/a>, <\/p>
It sounds like the sheet you're working in is a Project Sheet that has Resource Management connected<\/a> to it, and you're using the Resource Management Panel<\/strong><\/a> in Smartsheet to sync your data. This integration will use the Resource Management API to connect the two systems. <\/p>