Date+days not calculating correctly

Megan B.
Megan B.
edited 05/30/23 inFormulas and Functions

Hi all,

I need to add 21 days to a date referenced in another cell.

Ex: 10/15/23

When I use this formula: =DATE(YEAR([Projected Start Date]@row), MONTH([Projected Start Date]@row), (DAY([Projected Start Date]@row)) + 21) I receive an #INVALID VALUE

If I hardcode the date into the formula (=DATE(2023, 10, 15)+21, I return the right result (11/5/23)

All of the following formulas also return the correct response:

=DATE(YEAR([Projected Start Date]@row), 10, 15)+21

=DATE(YEAR([Projected Start Date]@row), MONTH([Projected Start Date]@row), 15) + 21

=DATE(YEAR([Projected Start Date]@row), MONTH([Projected Start Date]@row), (DAY([Projected Start Date]@row)) + 2) --(this returns a date of 10/17/23)

The problem seems to be when I use the DAY function + days that run the calculation into the next month but I am stumped because the same problem does not exist if I hard code the same date. It seems like somehow I need to get that numeric value to calculate first so the formula sees it only as a value and not a formula.

Edit to add:

I also tried using VALUE in the formula in this way:

=DATE(YEAR([Projected Start Date]@row), MONTH([Projected Start Date]@row), VALUE(DAY([Projected Start Date]@row)) + 21)

This was also unsuccessful.

Thoughts?

Best Answer

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the公式手册模板!
Try specifying an exact match within the MATCH function.<\/p>

=INDEX({Data SHPType}, MATCH(Course@row, {Data Course}, 0<\/strong>))<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":322,"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[]},{"discussionID":106455,"type":"question","name":"Formula to count items in a cell separated by a semicolon","excerpt":"Good afternoon, could someone help me with a formula to count items in a cell separated by a semicolon and put the total in another? I have a column called: \"MRA Actives codes\", in which there are different medical codes separated by a semicolon, for example: I70.0: Atherosclerosis of aorta; I50.9: Heart failure…","categoryID":322,"dateInserted":"2023-06-14T19:20:24+00:00","dateUpdated":null,"dateLastComment":"2023-06-15T11:46:15+00:00","insertUserID":162381,"insertUser":{"userID":162381,"name":"VirginiaLazor","title":"Medical Risk Adjustment Auditor","url":"https:\/\/community.smartsheet.com\/profile\/VirginiaLazor","photoUrl":"https:\/\/aws.smartsheet.com\/storageProxy\/image\/images\/u!1!b1Dom3_UQfo!xekpcXON8bo!9w33zAjZR8S","dateLastActive":"2023-06-15T12:10:22+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"updateUserID":null,"lastUserID":45516,"lastUser":{"userID":45516,"name":"Paul Newcome","title":"","url":"https:\/\/community.smartsheet.com\/profile\/Paul%20Newcome","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/082\/nQPUTVFKKWDJ2.jpg","dateLastActive":"2023-06-15T12:21:12+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":6,"countViews":39,"score":null,"hot":3373603599,"url":"https:\/\/community.smartsheet.com\/discussion\/106455\/formula-to-count-items-in-a-cell-separated-by-a-semicolon","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/106455\/formula-to-count-items-in-a-cell-separated-by-a-semicolon","format":"Rich","lastPost":{"discussionID":106455,"commentID":380725,"name":"Re: Formula to count items in a cell separated by a semicolon","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/380725#Comment_380725","dateInserted":"2023-06-15T11:46:15+00:00","insertUserID":45516,"insertUser":{"userID":45516,"name":"Paul Newcome","title":"","url":"https:\/\/community.smartsheet.com\/profile\/Paul%20Newcome","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/082\/nQPUTVFKKWDJ2.jpg","dateLastActive":"2023-06-15T12:21:12+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2023-06-15T12:03:29+00:00","dateAnswered":"2023-06-15T11:44:52+00:00","acceptedAnswers":[{"commentID":380724,"body":"

Hi @VirginiaLazor<\/a>,<\/p>

This should do the trick:<\/p>

=LEN([MRA ACTIVES CODES]@row) - LEN(SUBSTITUTE([MRA ACTIVES CODES]@row, \";\", \"//www.santa-greenland.com/community/discussion/105798/\"))<\/p>

This calculates the length of the MRA codes cell, then does the same if the semi-colons were removed and subtracts it to get the answer on how many of them there were.<\/p>

Hope this helps - if you have any issues then just post! 😊<\/span><\/p>"},{"commentID":380725,"body":"

If you remove the semi-colons and subtract that character count from the total character count WITH the semi-colons, that will tell you how many entries are in the cell.<\/p>


<\/p>

=LEN(Column Name]@row) - LEN(SUBSTITUTE([Column name]@row, \";\", \"//www.santa-greenland.com/community/discussion/105798/\"))<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":322,"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[]},{"discussionID":106453,"type":"question","name":"Row Status Indicator in Schedule","excerpt":"Wrote a formula to check two items and change and indicator light. Here is the code but it is saying incorrect argument set? =IF(Status@row <> \"Complete\", [Due Date]@row < TODAY(), \"Red\", IF(Status@row <> \"Complete\", [Due Date]@row >= TODAY(2), \"Yellow\", \"Green\")) I have reviewed everything multiple times and cannot figure…","categoryID":322,"dateInserted":"2023-06-14T19:15:28+00:00","dateUpdated":null,"dateLastComment":"2023-06-15T10:03:13+00:00","insertUserID":162256,"insertUser":{"userID":162256,"name":"delaurellc","title":"Senior Consultant","url":"https:\/\/community.smartsheet.com\/profile\/delaurellc","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-06-14T22:59:37+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"updateUserID":null,"lastUserID":91566,"lastUser":{"userID":91566,"name":"Genevieve P.","title":"Community Manager","url":"https:\/\/community.smartsheet.com\/profile\/Genevieve%20P.","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/KHY4Y67W0VRX\/nF76D5N9MFB28.png","dateLastActive":"2023-06-15T11:40:05+00:00","banned":0,"punished":0,"private":false,"label":"Employee Admin"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":2,"countViews":17,"score":null,"hot":3373594721,"url":"https:\/\/community.smartsheet.com\/discussion\/106453\/row-status-indicator-in-schedule","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/106453\/row-status-indicator-in-schedule","format":"Rich","lastPost":{"discussionID":106453,"commentID":380712,"name":"Re: Row Status Indicator in Schedule","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/380712#Comment_380712","dateInserted":"2023-06-15T10:03:13+00:00","insertUserID":91566,"insertUser":{"userID":91566,"name":"Genevieve P.","title":"Community Manager","url":"https:\/\/community.smartsheet.com\/profile\/Genevieve%20P.","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/KHY4Y67W0VRX\/nF76D5N9MFB28.png","dateLastActive":"2023-06-15T11:40:05+00:00","banned":0,"punished":0,"private":false,"label":"Employee Admin"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2023-06-15T10:03:03+00:00","dateAnswered":"2023-06-14T22:55:59+00:00","acceptedAnswers":[{"commentID":380684,"body":"

I figured out the code and here it is in case anyone is trying to do the same thing<\/p>

=IF(AND([Due Date]@row < TODAY(), Status@row <> \"Complete\"), \"Red\", IF(AND([Due Date]@row = TODAY(2), Status@row <> \"Complete\"), \"Yellow\", \"Green\"))<\/p>

Caroline<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":322,"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[]}],"initialPaging":{"nextURL":"https:\/\/community.smartsheet.com\/api\/v2\/discussions?page=2&categoryID=322&includeChildCategories=1&type%5B0%5D=Question&excludeHiddenCategories=1&sort=-hot&limit=3&expand%5B0%5D=all&expand%5B1%5D=-body&expand%5B2%5D=insertUser&expand%5B3%5D=lastUser&status=accepted","prevURL":null,"currentPage":1,"total":9995,"limit":3},"title":"Trending in Formulas and Functions ","subtitle":null,"description":null,"noCheckboxes":true,"containerOptions":[],"discussionOptions":[]}">