Resource Management: Handling of Milestones
I usually assign a resource to a Milestone (task with 0 duration), but now in RM for Smartsheet, if I do so, the resource is considered as 100% booked.
Form my point of view, if I do that, that should not be the case as the duration is 0. Or am I wrong?
Answers
-
Genevieve P. Employee Admin
Hi@Gabi
If you don't want the milestone to impact a team members utilization, I'd recommend setting the Allocation % for the milestone to 0%
Cheers,
Genevieve
Categories
I hope you're well and safe!<\/p>
Unfortunately, as far as I know, it's not possible now, but it's an excellent idea!<\/p>
Please submit this as a Product Feedback or Idea <\/strong>(If it hasn't been added already)<\/em><\/strong> when you have a moment.<\/strong><\/a><\/p>
Be safe, and have a fantastic week!<\/p>
Andrée Starå<\/strong><\/a> | Workflow Consultant \/ CEO @ WORK BOLD<\/strong><\/a><\/p>
Hi @Nkeiruka. Aguocha<\/a>, <\/p>
It sounds like the sheet you're working in is a Project Sheet that has Resource Management connected<\/a> to it, and you're using the Resource Management Panel<\/strong><\/a> in Smartsheet to sync your data. This integration will use the Resource Management API to connect the two systems. <\/p>