Hi,
I need to delink the Duration column from the Finish date in a schedule.
I'm creating a master / roll up schedule that is linking from multiple sheets, however I can't link the finish date as it's greyed out. It's dependent on the duration.
Is this possible? Are there any work arounds?
Best Answer
-
L_123 ✭✭✭✭✭✭
In gantt view there is a gear in the top right. click that and you can change dependencies.
Answers
-
L_123 ✭✭✭✭✭✭
In gantt view there is a gear in the top right. click that and you can change dependencies.
Categories
=IF(AND(MONTH([Start Date]@row)<= 1, YEAR([Start Date]@row)<= 2023, MONTH([End Date]@row)>= 1, YEAR([End Date]@row)>= 2023), [$ per month]@row)<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":321,"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[]},{"discussionID":108239,"type":"question","name":"Is an automated export of a Smartsheet to an Excel file possible?","excerpt":"Hi all, I have been having the most frustrating conversation with Smartsheet support on this topic and not getting answers to the question that I asked. I would like to set up an automation that will email me an Excel copy of my project plans on a weekly basis (or when triggered with a change - I don't really care) as I…","snippet":"Hi all, I have been having the most frustrating conversation with Smartsheet support on this topic and not getting answers to the question that I asked. I would like to set up an…","categoryID":321,"dateInserted":"2023-07-28T02:36:12+00:00","dateUpdated":null,"dateLastComment":"2023-07-28T06:42:13+00:00","insertUserID":164243,"insertUser":{"userID":164243,"name":"Candace G","title":"Senior Project Manager","url":"https:\/\/community.smartsheet.com\/profile\/Candace%20G","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-28T06:50:48+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"updateUserID":null,"lastUserID":137040,"lastUser":{"userID":137040,"name":"Gia Thinh","title":"","url":"https:\/\/community.smartsheet.com\/profile\/Gia%20Thinh","photoUrl":"https:\/\/aws.smartsheet.com\/storageProxy\/image\/images\/u!1!pXMt6Y5Kqjs!ZHDtmZp0Yms!Dwma-t47hzh","dateLastActive":"2023-07-28T15:25:22+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":3,"countViews":38,"score":null,"hot":3381040105,"url":"https:\/\/community.smartsheet.com\/discussion\/108239\/is-an-automated-export-of-a-smartsheet-to-an-excel-file-possible","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/108239\/is-an-automated-export-of-a-smartsheet-to-an-excel-file-possible","format":"Rich","tagIDs":[268,334,440,445,510],"lastPost":{"discussionID":108239,"commentID":387741,"name":"Re: Is an automated export of a Smartsheet to an Excel file possible?","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/387741#Comment_387741","dateInserted":"2023-07-28T06:42:13+00:00","insertUserID":137040,"insertUser":{"userID":137040,"name":"Gia Thinh","title":"","url":"https:\/\/community.smartsheet.com\/profile\/Gia%20Thinh","photoUrl":"https:\/\/aws.smartsheet.com\/storageProxy\/image\/images\/u!1!pXMt6Y5Kqjs!ZHDtmZp0Yms!Dwma-t47hzh","dateLastActive":"2023-07-28T15:25:22+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Get Help","url":"https:\/\/community.smartsheet.com\/categories\/get-help"},{"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2023-07-28T06:32:42+00:00","dateAnswered":"2023-07-28T05:49:42+00:00","acceptedAnswers":[{"commentID":387737,"body":"
Hi Candace,<\/p>
The answer is YES. You can use \"Send as Attachment\" feature in the File menu of your sheet to setup the schedule for your need. You should be a licensed user to use this feature as well (I remembered that). <\/p>
Hope this works for you.<\/p>