Stop people from tracking to a project when an hours or fee budget is exhausted
Hi Community!
Does anyone know if there is a way to set up a project in Resource Management so when the time or fee budget is exhausted, people can no longer track time to that project?
The only lock setting I am able to see if one to lock time entries to the project once added (or after 14 days). Not sure if I am just missing something obvious or if this isnt a feature.
Thanks!
Best Answer
-
Andrée Starå ✭✭✭✭✭✭
I hope you're well and safe!
Unfortunately, as far as I know, it's not possible now, but it's an excellent idea!
Did that work/help?
I hope that helps!
Be safe, and have a fantastic week!
Best,
Andrée Starå| Workflow Consultant / CEO @WORK BOLD
✅做米y post(s) help or answer your question or solve your problem? Please support the Community bymarking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå| Workflow Consultant / CEO @WORK BOLD
W:www.workbold.com| E:[email protected]| P: +46 (0) - 72 - 510 99 35
Feel free to contact me about help with Smartsheet, integrations, general workflow advice, or something else entirely.
Answers
-
L_123 ✭✭✭✭✭✭
you can lock rows based on a variety of criteria. you can add a helper checkbox column hidden in the background that uses a conditional to flag itself, then use that as the criteria for one.
https://help.smartsheet.com/articles/2479236-trigger-blocks-define-when-your-workflow-is-executed
-
Thanks for responding to my question@L_123!However, this does not answer my question. I was asking if there was a specific way to block tracking in Resource Management, not in Smartsheet.
If I were to lock a row in Smartsheet, the project and its budgeted hours or dollars would still be available to track towards in Resource Management.
Thanks!
B
-
Andrée Starå ✭✭✭✭✭✭
I hope you're well and safe!
Unfortunately, as far as I know, it's not possible now, but it's an excellent idea!
Did that work/help?
I hope that helps!
Be safe, and have a fantastic week!
Best,
Andrée Starå| Workflow Consultant / CEO @WORK BOLD
✅做米y post(s) help or answer your question or solve your problem? Please support the Community bymarking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå| Workflow Consultant / CEO @WORK BOLD
W:www.workbold.com| E:[email protected]| P: +46 (0) - 72 - 510 99 35
Feel free to contact me about help with Smartsheet, integrations, general workflow advice, or something else entirely.
-
Thanks for confirming@Andrée Starå!我将提交产品理念。ob欧宝娱乐app手机下载
-
Andrée Starå ✭✭✭✭✭✭
Excellent!
Happy to help!
✅Remember!做米y post(s) help or answer your question or solve your problem? Please support the Community bymarking it Insightful/Vote Up/Awesome or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå| Workflow Consultant / CEO @WORK BOLD
W:www.workbold.com| E:[email protected]| P: +46 (0) - 72 - 510 99 35
Feel free to contact me about help with Smartsheet, integrations, general workflow advice, or something else entirely.
Categories
I hope you're well and safe!<\/p>
Unfortunately, as far as I know, it's not possible now, but it's an excellent idea!<\/p>
Please submit this as a Product Feedback or Idea <\/strong>(If it hasn't been added already)<\/em><\/strong> when you have a moment.<\/strong><\/a><\/p>
Be safe, and have a fantastic week!<\/p>
Andrée Starå<\/strong><\/a> | Workflow Consultant \/ CEO @ WORK BOLD<\/strong><\/a><\/p>
Hi @Nkeiruka. Aguocha<\/a>, <\/p>
It sounds like the sheet you're working in is a Project Sheet that has Resource Management connected<\/a> to it, and you're using the Resource Management Panel<\/strong><\/a> in Smartsheet to sync your data. This integration will use the Resource Management API to connect the two systems. <\/p>