Can we use IFERROR and ISBLANK in the same formula together?
I want help for the following formula:
I want to divide two columns based on UniqueWorkstream column if it has any value. If the workstream column is blank, it should not show any value.
For that I have used the formula: =I=IF(ISBLANK([email protected]), " ", [Count of Tasks Overdue(Schedule)]@row / [Total Tasks(Schedule)]@row)
If both columns has zero, it is throwing an error #DIVIDE BY ZERO.
Best Answer
-
Andrée Starå ✭✭✭✭✭✭
Hi@sweta22
I hope you're well and safe!
Try something like this.
=IF([email protected]<> "", IFERROR([Count of Tasks Overdue(Schedule)]@row / [Total Tasks(Schedule)]@row, ""))
Did that work/help?
I hope that helps!
Be safe, and have a fantastic week!
Best,
Andrée Starå| Workflow Consultant / CEO @WORK BOLD
✅了我的帖子(s)帮助或回答你的问题吗tion or solve your problem? Please support the Community bymarking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå| Workflow Consultant / CEO @WORK BOLD
W:www.workbold.com| E:[email protected]| P: +46 (0) - 72 - 510 99 35
Feel free to contact me about help with Smartsheet, integrations, general workflow advice, or something else entirely.
Answers
-
Andrée Starå ✭✭✭✭✭✭
Hi@sweta22
I hope you're well and safe!
Try something like this.
=IF([email protected]<> "", IFERROR([Count of Tasks Overdue(Schedule)]@row / [Total Tasks(Schedule)]@row, ""))
Did that work/help?
I hope that helps!
Be safe, and have a fantastic week!
Best,
Andrée Starå| Workflow Consultant / CEO @WORK BOLD
✅了我的帖子(s)帮助或回答你的问题吗tion or solve your problem? Please support the Community bymarking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå| Workflow Consultant / CEO @WORK BOLD
W:www.workbold.com| E:[email protected]| P: +46 (0) - 72 - 510 99 35
Feel free to contact me about help with Smartsheet, integrations, general workflow advice, or something else entirely.
-
sweta22 ✭✭✭
@Andrée StaråThank you! That absolutely did the trick!
-
Andrée Starå ✭✭✭✭✭✭
Excellent!
Happy to help!
✅Remember!了我的帖子(s)帮助或回答你的问题吗tion or solve your problem? Please support the Community bymarking it Insightful/Vote Up/Awesome or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå| Workflow Consultant / CEO @WORK BOLD
W:www.workbold.com| E:[email protected]| P: +46 (0) - 72 - 510 99 35
Feel free to contact me about help with Smartsheet, integrations, general workflow advice, or something else entirely.
Categories
I hope you're well and safe!<\/p>
I can't see any rows in your screenshot that should be colored differently. Parent rows can't be changed.<\/p>
Can you share more screenshots with the conditional formatting options used on a few child rows?<\/strong> (Delete\/replace any confidential\/sensitive information before sharing) That would make it easier to help. <\/p> I hope that helps!<\/p> Be safe, and have a fantastic weekend!<\/p> Best,<\/p> Andrée Starå<\/strong><\/a> | Workflow Consultant \/ CEO @ WORK BOLD<\/strong><\/a><\/p> ✅Did my post(s) help or answer your question or solve your problem? Please support the Community by <\/em>marking it Insightful\/Vote Up, Awesome, or\/and as the accepted answer<\/em><\/strong>. It will make it easier for others to find a solution or help to answer!<\/em><\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":321,"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":219,"urlcode":"Sheets","name":"Sheets"},{"tagID":319,"urlcode":"functionality","name":"functionality"},{"tagID":437,"urlcode":"conditional-formatting","name":"Conditional Formatting"},{"tagID":439,"urlcode":"gantt-view","name":"Gantt View"}]},{"discussionID":108269,"type":"question","name":"Dashboard Metric Breaks on Update of DataShuttle","excerpt":"I am sure there is something I am missing. But I try to set a Dashboard Matrix on a field that is refreshed by Data Shuttle. But when the Grid refreshes it breaks the Metric and says Data missing even though there is data in the field. Is there anyway around this or does Data Shuttle always break a Metric Cell?","snippet":"I am sure there is something I am missing. But I try to set a Dashboard Matrix on a field that is refreshed by Data Shuttle. But when the Grid refreshes it breaks the Metric and…","categoryID":321,"dateInserted":"2023-07-28T17:52:38+00:00","dateUpdated":null,"dateLastComment":"2023-07-28T22:21:10+00:00","insertUserID":164293,"insertUser":{"userID":164293,"name":"Joshua Jones","title":"IT Specialist","url":"https:\/\/community.smartsheet.com\/profile\/Joshua%20Jones","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-28T22:18:30+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"updateUserID":null,"lastUserID":164293,"lastUser":{"userID":164293,"name":"Joshua Jones","title":"IT Specialist","url":"https:\/\/community.smartsheet.com\/profile\/Joshua%20Jones","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-28T22:18:30+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":2,"countViews":31,"score":null,"hot":3381150828,"url":"https:\/\/community.smartsheet.com\/discussion\/108269\/dashboard-metric-breaks-on-update-of-datashuttle","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/108269\/dashboard-metric-breaks-on-update-of-datashuttle","format":"Rich","tagIDs":[292,474],"lastPost":{"discussionID":108269,"commentID":387933,"name":"Re: Dashboard Metric Breaks on Update of DataShuttle","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/387933#Comment_387933","dateInserted":"2023-07-28T22:21:10+00:00","insertUserID":164293,"insertUser":{"userID":164293,"name":"Joshua Jones","title":"IT Specialist","url":"https:\/\/community.smartsheet.com\/profile\/Joshua%20Jones","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-28T22:18:30+00:00","banned":0,"punished":0,"private":false,"label":"✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Get Help","url":"https:\/\/community.smartsheet.com\/categories\/get-help"},{"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2023-07-28T22:21:14+00:00","dateAnswered":"2023-07-28T20:45:34+00:00","acceptedAnswers":[{"commentID":387914,"body":" How exactly is your Data Shuttle set up? If it is set to replace everything in the sheet when it runs, it is deleting the cell being referenced by the widget and then putting new data in new cells.<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":321,"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":292,"urlcode":"Dashboards","name":"Dashboards"},{"tagID":474,"urlcode":"data-shuttle","name":"Data Shuttle"}]},{"discussionID":108213,"type":"question","name":"How to spread costs evenly across months, if they fall within those dates","excerpt":"I have various financial line items that span different dates. I'd like the costs to be spread per month automatically based on the date and cost entry. I've tried various functions already, IF, AND, and it says Unpearsable. I'd like to spread out the costs in the Cost column to the months on the right, based on the start…","snippet":"I have various financial line items that span different dates. I'd like the costs to be spread per month automatically based on the date and cost entry. I've tried various…","categoryID":321,"dateInserted":"2023-07-27T19:03:42+00:00","dateUpdated":null,"dateLastComment":"2023-07-28T21:12:20+00:00","insertUserID":164209,"insertUser":{"userID":164209,"name":"AshwiniBiotech2023","title":"Sr. Director, Project Management","url":"https:\/\/community.smartsheet.com\/profile\/AshwiniBiotech2023","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-28T23:10:16+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"updateUserID":null,"lastUserID":164209,"lastUser":{"userID":164209,"name":"AshwiniBiotech2023","title":"Sr. Director, Project Management","url":"https:\/\/community.smartsheet.com\/profile\/AshwiniBiotech2023","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-28T23:10:16+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":14,"countViews":69,"score":null,"hot":3381071762,"url":"https:\/\/community.smartsheet.com\/discussion\/108213\/how-to-spread-costs-evenly-across-months-if-they-fall-within-those-dates","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/108213\/how-to-spread-costs-evenly-across-months-if-they-fall-within-those-dates","format":"Rich","lastPost":{"discussionID":108213,"commentID":387925,"name":"Re: How to spread costs evenly across months, if they fall within those dates","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/387925#Comment_387925","dateInserted":"2023-07-28T21:12:20+00:00","insertUserID":164209,"insertUser":{"userID":164209,"name":"AshwiniBiotech2023","title":"Sr. Director, Project Management","url":"https:\/\/community.smartsheet.com\/profile\/AshwiniBiotech2023","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-28T23:10:16+00:00","banned":0,"punished":0,"private":false,"label":"✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Get Help","url":"https:\/\/community.smartsheet.com\/categories\/get-help"},{"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B"}],"groupID":null,"statusID":3,"image":{"url":"https:\/\/us.v-cdn.net\/6031209\/uploads\/IBAVVE3YLO8D\/image.png","urlSrcSet":{"10":"","300":"","800":"","1200":"","1600":""},"alt":"image.png"},"attributes":{"question":{"status":"accepted","dateAccepted":"2023-07-28T09:38:32+00:00","dateAnswered":"2023-07-27T19:21:12+00:00","acceptedAnswers":[{"commentID":387646,"body":" You would use the below for Jan 2023 and adjust the month and year numbers accordingly for each of the other months.<\/p> =IF(AND(MONTH([Start Date]@row)<= 1, YEAR([Start Date]@row)<= 2023, MONTH([End Date]@row)>= 1, YEAR([End Date]@row)>= 2023), [$ per month]@row)<\/p>"},{"commentID":387901,"body":" Lets try a different approach.<\/p> =IF(AND(VALUE(YEAR([Start Date]@row) + IF(MONTH(Start Date]@row)< 10, \"0\", \"//www.santa-greenland.com/community/discussion/108163/\") + MONTH([Start Date]@row))<= 202307<\/strong>, VALUE(YEAR([End Date]@row) + IF(MONTH([End Date]@row)< 10, \"0\", \"//www.santa-greenland.com/community/discussion/108163/\") + MONTH([End Date]@row))>= 202307<\/strong>), [$ per month]@row)<\/p> Basically we are creating a yyyymm stamp from the start and end dates and comparing them to the yyyymm stamp for that year\/month combo. The above is for July 2023 (202307).<\/p>"},{"commentID":387906,"body":"
<\/p>