I use Datamesh to update from one sheet to another and then back again. Been successful with these two sheets for a year. Suddenly I'm getting the errors:
Error! Failed to issue the request, please relogin and try again.
Error code: 0 - Error message:error
This only happens one direction. I can datamesh from Sheet A to Sheet B but can no longer go from Sheet B to Sheet A. I have deleted all rows and columns so I'm down to 13 rows and 75 columns. This was working when there were 900 rows!
I wanted to use my target sheet with Resource Management so I turned DEPENDENCIES on in the PROJECT SETTINGS.
My DataMesh was trying to update the START and END dates (which now were driven automatically in the target sheet) from the source sheet so Smartsheet could not update cells which were automatically updated.
Once I turned DEPENDENCIES off in the target sheet my DataMesh worked just fine.
✅了我的帖子(s)帮助或回答你的问题吗tion or solve your problem? Please support the Community bymarking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
Thank you. I have indeed created a support ticket. Also, turns out it is the TARGET sheet which is failing. And the target sheet is very clean with no external links except to one link TO the source sheet. Fewer than 100 rows and fewer than 25 columns.
I wanted to use my target sheet with Resource Management so I turned DEPENDENCIES on in the PROJECT SETTINGS.
My DataMesh was trying to update the START and END dates (which now were driven automatically in the target sheet) from the source sheet so Smartsheet could not update cells which were automatically updated.
Once I turned DEPENDENCIES off in the target sheet my DataMesh worked just fine.
✅Remember!了我的帖子(s)帮助或回答你的问题吗tion or solve your problem? Please support the Community bymarking it Insightful/Vote Up/Awesome or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
I wanted to use my target sheet with Resource Management so I turned DEPENDENCIES on in the PROJECT SETTINGS. <\/p>
My DataMesh was trying to update the START and END dates (which now were driven automatically in the target sheet) from the source sheet so Smartsheet could not update cells which were automatically updated.<\/p>
Once I turned DEPENDENCIES off in the target sheet my DataMesh worked just fine.<\/p>