Future Developments

Will Kidwell
edited 12/09/19 inArchived 2016 Posts

I am a new user to Smartsheet. Still testing it out for the 30-Day Trial.

I really like Smartsheet, but am a bit concerned about becoming too involved with it because it does lack some functionality I was hoping for. That said, only a few of the upper end (expensive) project management programs seem to do what I want.

There are three things that seem to be missing:

1.) Ability to set a baseline, track actual performance stats against the baseline, and do a variance analysis of progress between actual vs projected goals.

2.) A clock for scheduling. Right now, Smartsheet will look at days, hours and mins, but it doesnt seem to let one schedule start and stop times for particular within a particular day. This is actually a pretty basic feature in day planners and calendars, so maybe I am missing something...

3.) What I'll call a "Project Journal", which would basically be a document organizer, or document management system, possibly with version control. Smartsheet already has the ability to upload and manage documents, which is functionality I am still learning, but it seems pretty basic for what I have seen so far.

All that said, Smartsheet is really a sweet system, and I wonder if there are plans to add in any of this type of functionality?

Thank you!

wm

Comments

  • J. Craig Williams
    J. Craig Williams ✭✭✭✭✭✭

    Will,

    I can't answer for Smartsheet, but you can always see what's coming soon here:

    //www.santa-greenland.com/product-roadmap

    In addition, Travis is the Smartsheet Community Manager and is on daily if not more often. He passes all enhancement requests to the development team. They get on here too to keep an eye out for feature requests.

    For (1), I set up this manually, saving the start and end date columns for later comparisons. Another column or two for the variance and you get pretty much what you need if not what you want. I do the same with the cost.

    For (3), I like Smartsheet's simplicity for documentation control. I've worked with two very expensive systems for doc control and for both heard nothing but complaints from other users. When you upload a document, Smartsheet will version it if it has the same name as one already uploaded in the same place or create a new instance (it will ask you). I really like that.

    And attachments can be in three places - workspaces, sheets, or rows.

    It also syncs with Google Docs, which might be worth a look.

    Hope this helps.


    Craig

  • Travis
    Travis Employee

    你好,很高兴听到你正在测试Smartsheet! We are always working to improve the product and I will make sure I pass your feedback along. We do plan on adding additional scheduling tools in the future although I am not exactly sure how they will function.

    As a workaround for a couple of these, Craig mentioned a good workaround for baseline. Clock scheduling, you can add a Text/Number column and manually track start and end times for tasks. For the file organizer, we do integrate with Drive, Box, Dropbox, and Egnyte - which do support file structures. You could build the structures in one of these services then link the files to sheets as needed through our integration.

This discussion has been closed.
Hi Robin,<\/p>


<\/p>

Current options are only to take screenshot or print the dashboard as a PDF or to One Note. However, there already is a planned enhancement in the roadmap to send the dashboard snapshot via a scheduled email (similar to reports). No timelines have been mentioned as yet.<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":321,"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[]},{"discussionID":107055,"type":"question","name":"Fill in project number based on ancestor level","excerpt":"I want to auto fill the project_number between the the Purple and Red rows. So all the children of Purple Project have a Project_Number = 4 and all the Red Children have a Project_number of 7 Tried using something like this. So if the Project is checked return the Project_Number. This give me \"UNPARSABLE\"…","snippet":"I want to auto fill the project_number between the the Purple and Red rows. So all the children of Purple Project have a Project_Number = 4 and all the Red Children have a…","categoryID":322,"dateInserted":"2023-06-28T20:28:32+00:00","dateUpdated":null,"dateLastComment":"2023-06-29T12:31:20+00:00","insertUserID":124423,"insertUser":{"userID":124423,"name":"Julie Fleming","url":"https:\/\/community.smartsheet.com\/profile\/Julie%20Fleming","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-06-29T12:31:11+00:00","banned":0,"punished":0,"private":false,"label":"✭✭"},"updateUserID":null,"lastUserID":124423,"lastUser":{"userID":124423,"name":"Julie Fleming","url":"https:\/\/community.smartsheet.com\/profile\/Julie%20Fleming","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-06-29T12:31:11+00:00","banned":0,"punished":0,"private":false,"label":"✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":3,"countViews":22,"score":null,"hot":3376027792,"url":"https:\/\/community.smartsheet.com\/discussion\/107055\/fill-in-project-number-based-on-ancestor-level","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/107055\/fill-in-project-number-based-on-ancestor-level","format":"Rich","tagIDs":[254],"lastPost":{"discussionID":107055,"commentID":383057,"name":"Re: Fill in project number based on ancestor level","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/383057#Comment_383057","dateInserted":"2023-06-29T12:31:20+00:00","insertUserID":124423,"insertUser":{"userID":124423,"name":"Julie Fleming","url":"https:\/\/community.smartsheet.com\/profile\/Julie%20Fleming","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-06-29T12:31:11+00:00","banned":0,"punished":0,"private":false,"label":"✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions"}],"groupID":null,"statusID":3,"image":{"url":"https:\/\/us.v-cdn.net\/6031209\/uploads\/MQEUGWPAA2YV\/image.png","urlSrcSet":{"10":"","300":"","800":"","1200":"","1600":""},"alt":"image.png"},"attributes":{"question":{"status":"accepted","dateAccepted":"2023-06-29T12:31:08+00:00","dateAnswered":"2023-06-28T23:12:12+00:00","acceptedAnswers":[{"commentID":382982,"body":"

Hi Julie,<\/p>

If your primary column is always going to have the text \"#...\" at the end of the field for the first parent row in each group, you should be able to use the \"#\" as a starting point to reference in a RIGHT function. In this case, the below formula should work as a column formula in the Project_Number column. You will just need to substitute your column name \"Project\\Epic\\Feature\\Sprint Objectives\\Task\" wherever it says Primary Column.<\/p>

=IF(COUNT(ANCESTORS([Primary Column]@row)) = 0, RIGHT([Primary Column]@row, LEN([Primary Column]@row) - FIND(\"#\", [Primary Column]@row)), PARENT([Project_Number]@row))<\/p>

Using the LEN - FIND functions should keep the formula working correctly as you get into multiple-digit project numbers. Keep in mind that this formula will need to be updated if the text \"#...\" is ever omitted\/changed in the primary column or if it is not the rightmost text in the field.<\/p>

Hope this works for you! 😊<\/span><\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":322,"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":254,"urlcode":"Formulas","name":"Formulas"}]},{"discussionID":107046,"type":"question","name":"How to add project dashboard link to project metadata sheet when using PMO template","excerpt":"Need some help here. Set up the PMO using the PMO template. PMs have added projects but the project dashboard hyperlink never populated in the intake sheet nor the project metadata. Trying to add that in now, as the project plan is already created. I've tried to hyperlink the project dashboard URL, copy\/past the URL in the…","snippet":"Need some help here. Set up the PMO using the PMO template. PMs have added projects but the project dashboard hyperlink never populated in the intake sheet nor the project…","categoryID":343,"dateInserted":"2023-06-28T18:45:39+00:00","dateUpdated":null,"dateLastComment":"2023-06-29T12:11:09+00:00","insertUserID":162917,"insertUser":{"userID":162917,"name":"swaters","url":"https:\/\/community.smartsheet.com\/profile\/swaters","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-06-28T18:54:58+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"updateUserID":null,"lastUserID":45516,"lastUser":{"userID":45516,"name":"Paul Newcome","title":"","url":"https:\/\/community.smartsheet.com\/profile\/Paul%20Newcome","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/082\/nQPUTVFKKWDJ2.jpg","dateLastActive":"2023-06-29T12:50:07+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":3,"countViews":13,"score":null,"hot":3376020408,"url":"https:\/\/community.smartsheet.com\/discussion\/107046\/how-to-add-project-dashboard-link-to-project-metadata-sheet-when-using-pmo-template","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/107046\/how-to-add-project-dashboard-link-to-project-metadata-sheet-when-using-pmo-template","format":"Rich","lastPost":{"discussionID":107046,"commentID":383038,"name":"Re: How to add project dashboard link to project metadata sheet when using PMO template","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/383038#Comment_383038","dateInserted":"2023-06-29T12:11:09+00:00","insertUserID":45516,"insertUser":{"userID":45516,"name":"Paul Newcome","title":"","url":"https:\/\/community.smartsheet.com\/profile\/Paul%20Newcome","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/082\/nQPUTVFKKWDJ2.jpg","dateLastActive":"2023-06-29T12:50:07+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Using Smartsheet","url":"https:\/\/community.smartsheet.com\/categories\/using-smartsheet"},{"name":"Add Ons and Integrations","url":"https:\/\/community.smartsheet.com\/categories\/apps-and-integrations"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2023-06-29T10:26:58+00:00","dateAnswered":"2023-06-28T18:54:05+00:00","acceptedAnswers":[{"commentID":382940,"body":"

Right click on the cell, select \"Hyperlink\", select \"Link to other Smartsheet\", click on \"select sheet>\", then select the dashboard to want to create the hyperlink to. You can also adjust the displayed text if needed.<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":343,"name":"Add Ons and Integrations","url":"https:\/\/community.smartsheet.com\/categories\/apps-and-integrations","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[]}],"initialPaging":{"nextURL":"https:\/\/community.smartsheet.com\/api\/v2\/discussions?page=2&includeChildCategories=1&type%5B0%5D=Question&excludeHiddenCategories=1&siteSectionID=0&sort=-hot&limit=3&expand%5B0%5D=all&expand%5B1%5D=-body&expand%5B2%5D=insertUser&expand%5B3%5D=lastUser&status=accepted","prevURL":null,"currentPage":1,"total":10000,"limit":3},"title":"Trending Posts","subtitle":null,"description":null,"noCheckboxes":true,"containerOptions":[],"discussionOptions":[]}">