Setting a project due date, then building tasks with predecessors leading into it - not working righ
I know there is a way to do this but for some reason I am stuck. I have an event taking place on 5/25. So that needs to be the due date and it CAN NOT MOVE. I then have maybe 40 or so tasks leading up to it, all of which have to occur in certain sequences. I am not able to set up the project. One of two problems occurs. Either I enter a dependency and all of my dates vanish. Or if I enter dummy dates on all tasks (which is about as anti-project management as it gets), and THEN attempt to sequence them, those dates stay in place while forcing my event due date outward, when the opposite should occure. The task dates need to all move back in time in order to accommodate the project due date. Anyone know what I am obviously missing here? I am used to traditional PMIS systems that can all do this so maybe I just need to retrain my mind here? Thanks to whomever can help.
Comments
-
J. Craig Williams ✭✭✭✭✭✭
JP,
Like most PM software, Smartsheet allows predecessor types.
Default is FS (finish to start), but the others are available too.
You want to build backwards using SF type.
See this article on more.
//www.santa-greenland.com/blog/support-tip-work-back-schedule
Craig
-
Hi Craig - that is actually what I had ben doing for a while now. I just happened to notice the gantt flow, although LOOKED ok, was flowing backwards upward to the left. =D
Is this the only way to make Smartsheets cooperate like this?
Thanks for the input!
-
J. Craig Williams ✭✭✭✭✭✭
To my understanding, yes, the arrows look different.
Be aware, also, that the critical path is easily shown 'broken' on reverse tasks.
Smartsheet is aware and I hope they fix it soon.
Craig
-
Me too but I think it has been this way for a while so I'm not even sure they have considered it as a "fix". I can just ignore the arrows and pretend the timeline is flowing foward but one of our new PM's just asked me the other day "Why are the arrows flowing backward?" =O As much as a like Smartsheet, this one is really bugging me for some reason. Thanks for the feedback!
Categories
I hope you're well and safe!<\/p>
I can't see any rows in your screenshot that should be colored differently. Parent rows can't be changed.<\/p>
Can you share more screenshots with the conditional formatting options used on a few child rows?<\/strong> (Delete\/replace any confidential\/sensitive information before sharing) That would make it easier to help. <\/p> I hope that helps!<\/p> Be safe, and have a fantastic weekend!<\/p> Best,<\/p> Andrée Starå<\/strong><\/a> | Workflow Consultant \/ CEO @ WORK BOLD<\/strong><\/a><\/p> ✅Did my post(s) help or answer your question or solve your problem? Please support the Community by <\/em>marking it Insightful\/Vote Up, Awesome, or\/and as the accepted answer<\/em><\/strong>. It will make it easier for others to find a solution or help to answer!<\/em><\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":321,"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":219,"urlcode":"Sheets","name":"Sheets"},{"tagID":319,"urlcode":"functionality","name":"functionality"},{"tagID":437,"urlcode":"conditional-formatting","name":"Conditional Formatting"},{"tagID":439,"urlcode":"gantt-view","name":"Gantt View"}]},{"discussionID":108278,"type":"question","name":"How do you calculate the average number of days between a submitted date and a start date?","excerpt":"Additional context: We use Smartsheet to track support requests from the organization. We have an automated column that records the day the form is filled out. The form also has a date range of when they need their request completed by. I would like to calculate the average amount of days people provide from the day they…","snippet":"Additional context: We use Smartsheet to track support requests from the organization. We have an automated column that records the day the form is filled out. The form also has a…","categoryID":322,"dateInserted":"2023-07-28T20:36:42+00:00","dateUpdated":null,"dateLastComment":"2023-07-28T21:00:45+00:00","insertUserID":128090,"insertUser":{"userID":128090,"name":"Carlos Fernandez-Torres","url":"https:\/\/community.smartsheet.com\/profile\/Carlos%20Fernandez-Torres","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-28T21:30:09+00:00","banned":0,"punished":0,"private":false,"label":"✭✭"},"updateUserID":null,"lastUserID":45516,"lastUser":{"userID":45516,"name":"Paul Newcome","title":"","url":"https:\/\/community.smartsheet.com\/profile\/Paul%20Newcome","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/082\/nQPUTVFKKWDJ2.jpg","dateLastActive":"2023-07-29T11:58:40+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":3,"countViews":27,"score":null,"hot":3381156447,"url":"https:\/\/community.smartsheet.com\/discussion\/108278\/how-do-you-calculate-the-average-number-of-days-between-a-submitted-date-and-a-start-date","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/108278\/how-do-you-calculate-the-average-number-of-days-between-a-submitted-date-and-a-start-date","format":"Rich","tagIDs":[254],"lastPost":{"discussionID":108278,"commentID":387924,"name":"Re: How do you calculate the average number of days between a submitted date and a start date?","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/387924#Comment_387924","dateInserted":"2023-07-28T21:00:45+00:00","insertUserID":45516,"insertUser":{"userID":45516,"name":"Paul Newcome","title":"","url":"https:\/\/community.smartsheet.com\/profile\/Paul%20Newcome","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/082\/nQPUTVFKKWDJ2.jpg","dateLastActive":"2023-07-29T11:58:40+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Get Help","url":"https:\/\/community.smartsheet.com\/categories\/get-help"},{"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions"}],"groupID":null,"statusID":3,"image":{"url":"https:\/\/us.v-cdn.net\/6031209\/uploads\/QO67SBLMOJQA\/image.png","urlSrcSet":{"10":"","300":"","800":"","1200":"","1600":""},"alt":"image.png"},"attributes":{"question":{"status":"accepted","dateAccepted":"2023-07-28T21:01:27+00:00","dateAnswered":"2023-07-28T21:00:45+00:00","acceptedAnswers":[{"commentID":387924,"body":" =[End Date]@row - [Start Date]@row<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":322,"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":254,"urlcode":"Formulas","name":"Formulas"}]},{"discussionID":108269,"type":"question","name":"Dashboard Metric Breaks on Update of DataShuttle","excerpt":"I am sure there is something I am missing. But I try to set a Dashboard Matrix on a field that is refreshed by Data Shuttle. But when the Grid refreshes it breaks the Metric and says Data missing even though there is data in the field. Is there anyway around this or does Data Shuttle always break a Metric Cell?","snippet":"I am sure there is something I am missing. But I try to set a Dashboard Matrix on a field that is refreshed by Data Shuttle. But when the Grid refreshes it breaks the Metric and…","categoryID":321,"dateInserted":"2023-07-28T17:52:38+00:00","dateUpdated":null,"dateLastComment":"2023-07-28T22:21:10+00:00","insertUserID":164293,"insertUser":{"userID":164293,"name":"Joshua Jones","title":"IT Specialist","url":"https:\/\/community.smartsheet.com\/profile\/Joshua%20Jones","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-28T22:18:30+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"updateUserID":null,"lastUserID":164293,"lastUser":{"userID":164293,"name":"Joshua Jones","title":"IT Specialist","url":"https:\/\/community.smartsheet.com\/profile\/Joshua%20Jones","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-28T22:18:30+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":2,"countViews":32,"score":null,"hot":3381150828,"url":"https:\/\/community.smartsheet.com\/discussion\/108269\/dashboard-metric-breaks-on-update-of-datashuttle","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/108269\/dashboard-metric-breaks-on-update-of-datashuttle","format":"Rich","tagIDs":[292,474],"lastPost":{"discussionID":108269,"commentID":387933,"name":"Re: Dashboard Metric Breaks on Update of DataShuttle","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/387933#Comment_387933","dateInserted":"2023-07-28T22:21:10+00:00","insertUserID":164293,"insertUser":{"userID":164293,"name":"Joshua Jones","title":"IT Specialist","url":"https:\/\/community.smartsheet.com\/profile\/Joshua%20Jones","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-28T22:18:30+00:00","banned":0,"punished":0,"private":false,"label":"✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Get Help","url":"https:\/\/community.smartsheet.com\/categories\/get-help"},{"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2023-07-28T22:21:14+00:00","dateAnswered":"2023-07-28T20:45:34+00:00","acceptedAnswers":[{"commentID":387914,"body":" How exactly is your Data Shuttle set up? If it is set to replace everything in the sheet when it runs, it is deleting the cell being referenced by the widget and then putting new data in new cells.<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":321,"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":292,"urlcode":"Dashboards","name":"Dashboards"},{"tagID":474,"urlcode":"data-shuttle","name":"Data Shuttle"}]}],"initialPaging":{"nextURL":"https:\/\/community.smartsheet.com\/api\/v2\/discussions?page=2&includeChildCategories=1&type%5B0%5D=Question&excludeHiddenCategories=1&siteSectionID=0&sort=-hot&limit=3&expand%5B0%5D=all&expand%5B1%5D=-body&expand%5B2%5D=insertUser&expand%5B3%5D=lastUser&status=accepted","prevURL":null,"currentPage":1,"total":10000,"limit":3},"title":"Trending Posts","subtitle":null,"description":null,"noCheckboxes":true,"containerOptions":[],"discussionOptions":[]}">