Setting date in Project profile data from Master intake form

Am I missing something? I've been trying to push the start date of a project from the intake sheet (via intake form date input field) without success.
Upon spinning up the project in SCC, I get the error:
- Failed to update template field(s) for "Project Profile Data" (Code: 5536 - Message: The value "04-27-2018" could not be saved in column "Start Date". This column is restricted to ABSTRACT_DATETIME values only. )
Which, to me, says that the date field from the form is not sending the correct format of date to the Project profile data sheet. The regional (default format) is "04/27/18" as opposed to 04-27-2018
There might be some work-around for this by separating the schedule information and gantt from the profile data.. however this would introduce other problems (like pushing an updated date to the overall summary sheet whenever someone changes a task date in a project). Also, I really don't want to make it a two-three step process just to submit a project that should begin or end on a certain date.
TLDR: Setting date in form. Using Control Center to make project. Date not being injected correctly. Any pointers?
Comments
-
Alejandra Employee
Hi Ezra,
ABSTRACT_DATETIME is a project date value inISO-8601format: 2019-07-01
If needed, more information on this can be found here:https://smartsheet-platform.github.io/api-docs/#cell-reference
-
Ezra ✭✭✭
Thanks, Alejandra.. however I'm not writing an API addon, just trying to take a date entered by a Smartsheet user in a Smartsheet form as a project "start" date. But every time I think I have it, Smartsheet complains about the format. I've even tried pulling it apart and reformatting the ISO8601 format (YYYY-MM-DDTHH:MM:SSZ) to read as MM/DD/YY - but that doesn't work either.
Categories
No, it currently isn't possible to share the Data Shuttle workflow configuration with another account. The set-up for that workflow is associated with one account. (Please let our Product team know of your feature request by filling in this form, here!)<\/a><\/p>
If you are looking to transfer workflows because a user has left the organization, you could potentially update the Primary email address associated with the account that owns the configurations. This will allow you to gain access to the Data Shuttle workflows from the new email. Keep in mind this would need to be an email that does not currently have a Smartsheet account. See: Admin Center: Add, Edit, and Delete Individual Users with User Management<\/a><\/p>