H Folks,
For some reason I have areas in my smartsheet plan that have grid missing, some are ok.
Does anyone have an idea how I can correct this and add the gridelines back please.
thanks
Mark,
Comments
-
Andrée Starå ✭✭✭✭✭✭
Hi Mark,
That looks strange! Have you tried logging out/in? Is it only in one sheet it's showing like that? What are on those rows?
If you haven’t already, I would recommend that you reach out to the Smartsheet Support Team.Smartsheet Support Team
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå| Workflow Consultant / CEO @WORK BOLD
W:www.workbold.com| E:[email protected]| P: +46 (0) - 72 - 510 99 35
Feel free to contact me about help with Smartsheet, integrations, general workflow advice, or something else entirely.
-
Eric M Oliveira Employee
Hello,
Happy to help investigate why some Gantt View grid lines are not appearing for some rows. The most common reason this occurs is that the row's background has been set to white utilizing the paint bucket tool in the toolbar. To correct this, select the row, then the paint bucket 'background' tool and set it to 'Automatic' instead of white. This will likely correct the issue.
Have a wonderful day. Thank you for contacting Smartsheet Support.
Cheers,
Eric
Smartsheet Technical Support
-
Paul Ayres ✭✭
Thank you for that Eric, I have always wondered why that happened. Just made some adjustments to my conditional formatting and all now appears correctly. White fill was the culprit. Much appreciated.
Cheers, Paul
F&P Healthcare, New Zealand.
Categories
This has to do with how a milestone is represented (ie. a 0 day duration). If you hard type milestone without a predecessor or successor, it will show up as the beginning of that day instead of the end of the day. If you have a milestone that is following a standard finish to start logic, it will show up at the end of the previous activity. <\/p>
So, Task B4 in the backwards version is actually saying that the completion happened in the 00:00 hr of that day. if you put any activity in that has a duration and uses the start to finish relationship, that activity will naturally finish at the end of the previous day. So, to get your example above to work, the finishing task would need to be 1 day long so it takes up the full work day. I found it easier to visualize if you zoom all the way in on the gantt chart so you can see the diamond symbol of the milestone at the beginning and end of the days when used in different set ups.<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":321,"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[]},{"discussionID":108291,"type":"question","name":"Conditional formatting in Gantt not working with dependencies","excerpt":"For some reason it seems like my conditional formatting rules aren't being applied to certain rows in the Gantt chart side of this sheet. The problem is resolved if I disable dependencies, but I need those and don't understand why this should matter since I don't have any rules related to status or % complete in the…","snippet":"For some reason it seems like my conditional formatting rules aren't being applied to certain rows in the Gantt chart side of this sheet. The problem is resolved if I disable…","categoryID":321,"dateInserted":"2023-07-29T22:50:55+00:00","dateUpdated":null,"dateLastComment":"2023-07-30T15:38:08+00:00","insertUserID":164323,"insertUser":{"userID":164323,"name":"smbailey","title":"Senior Business Systems Analyst","url":"https:\/\/community.smartsheet.com\/profile\/smbailey","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-30T15:36:49+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"updateUserID":null,"lastUserID":164323,"lastUser":{"userID":164323,"name":"smbailey","title":"Senior Business Systems Analyst","url":"https:\/\/community.smartsheet.com\/profile\/smbailey","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-30T15:36:49+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":3,"countViews":33,"score":null,"hot":3381404343,"url":"https:\/\/community.smartsheet.com\/discussion\/108291\/conditional-formatting-in-gantt-not-working-with-dependencies","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/108291\/conditional-formatting-in-gantt-not-working-with-dependencies","format":"Rich","tagIDs":[219,319,437,439],"lastPost":{"discussionID":108291,"commentID":387971,"name":"Re: Conditional formatting in Gantt not working with dependencies","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/387971#Comment_387971","dateInserted":"2023-07-30T15:38:08+00:00","insertUserID":164323,"insertUser":{"userID":164323,"name":"smbailey","title":"Senior Business Systems Analyst","url":"https:\/\/community.smartsheet.com\/profile\/smbailey","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-30T15:36:49+00:00","banned":0,"punished":0,"private":false,"label":"✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Get Help","url":"https:\/\/community.smartsheet.com\/categories\/get-help"},{"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B"}],"groupID":null,"statusID":3,"image":{"url":"https:\/\/us.v-cdn.net\/6031209\/uploads\/4N6Y1NCLVR43\/2023-07-29-15-46-58-281-29-moving-plan-smartsheet-com.png","urlSrcSet":{"10":"","300":"","800":"","1200":"","1600":""},"alt":"2023-07-29 15_46_58-(1) Moving plan - Smartsheet.com.png"},"attributes":{"question":{"status":"accepted","dateAccepted":"2023-07-30T15:39:24+00:00","dateAnswered":"2023-07-30T09:21:36+00:00","acceptedAnswers":[{"commentID":387967,"body":"
Hi @smbailey<\/a> <\/p> I hope you're well and safe!<\/p> I can't see any rows in your screenshot that should be colored differently. Parent rows can't be changed.<\/p> Can you share more screenshots with the conditional formatting options used on a few child rows?<\/strong> (Delete\/replace any confidential\/sensitive information before sharing) That would make it easier to help. <\/p> I hope that helps!<\/p> Be safe, and have a fantastic weekend!<\/p> Best,<\/p> Andrée Starå<\/strong><\/a> | Workflow Consultant \/ CEO @ WORK BOLD<\/strong><\/a><\/p> ✅Did my post(s) help or answer your question or solve your problem? Please support the Community by <\/em>marking it Insightful\/Vote Up, Awesome, or\/and as the accepted answer<\/em><\/strong>. It will make it easier for others to find a solution or help to answer!<\/em><\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":321,"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":219,"urlcode":"Sheets","name":"Sheets"},{"tagID":319,"urlcode":"functionality","name":"functionality"},{"tagID":437,"urlcode":"conditional-formatting","name":"Conditional Formatting"},{"tagID":439,"urlcode":"gantt-view","name":"Gantt View"}]}],"initialPaging":{"nextURL":"https:\/\/community.smartsheet.com\/api\/v2\/discussions?page=2&categoryID=321&includeChildCategories=1&type%5B0%5D=Question&excludeHiddenCategories=1&sort=-hot&limit=3&expand%5B0%5D=all&expand%5B1%5D=-body&expand%5B2%5D=insertUser&expand%5B3%5D=lastUser&status=accepted","prevURL":null,"currentPage":1,"total":4897,"limit":3},"title":"Trending in Smartsheet Basics","subtitle":null,"description":null,"noCheckboxes":true,"containerOptions":[],"discussionOptions":[]}">