DataMesh & Gantt Charts

I am working on a project that we are trying to DataMesh two individual Gantt schedules into one new worksheet together. I've not DataMeshed too much, but is this possible? I use a formula of "Row # + Site #" as my unique identifier for the config. I set up the config, and the first time I kept on getting errors, so I removed the predecessors, thinking that might've messed it up. But now just using basic information like Start/End Date and a description, the Config has been "Loading..." for 25+ minutes. So is it possible to DataMesh Gantt schedules, or is there something on the technical side preventing this?
To answer the obvious questions, for muddy reasons, we don't want to just manually copy/paste the two Gantt schedules into one Worksheet.
Jason Tarpinian -Sevan Technology
Smartsheet Platinum Partner
Comments
-
IanN Employee
Hello Jason,
For questions with errors that DataMesh is throwing, it's probably best to work directly with our Support Team:https://help.smartsheet.com/contact.
There are a few things you'd want to check, but the likeliest would be that when using a sheet with Dependencies enabled (Gantts are usually dependency enabled), there are two limitations (http://smartsheet-platform.github.io/api-docs/#update-rows):
- End Date cells can't be updated via the API on Dependency enabled sheets
- Start Date cellswith a Predecessoralso can't be updated via the API.
基本上,你可以a Start Date and a Duration when you sync it over. Smartsheet will automatically create the End Date for you.
See if you can only map the Start and Duration fields and then run the DataMesh again. If you run into further problems, I recommend submitting a ticket at the very top URL.
Thanks!
Ian
Categories
No, it currently isn't possible to share the Data Shuttle workflow configuration with another account. The set-up for that workflow is associated with one account. (Please let our Product team know of your feature request by filling in this form, here!)<\/a><\/p>
If you are looking to transfer workflows because a user has left the organization, you could potentially update the Primary email address associated with the account that owns the configurations. This will allow you to gain access to the Data Shuttle workflows from the new email. Keep in mind this would need to be an email that does not currently have a Smartsheet account. See: Admin Center: Add, Edit, and Delete Individual Users with User Management<\/a><\/p>