I want task duration to ignore non-working days
Comments
-
L_123 ✭✭✭✭✭✭
As far as setting the standard work week, have you looked a the project settings? Right click any column headers, then select edit project settings. You can play around with the settings in there to get what you want if I am understanding your question correctly.
For removing the task I would have to see how the sheet is set up in order to give you a better answer.
-
Sorry about that. I don't think I made much sense originally. I will try to explain it better.
I have attached a screenshot of my Gantt chart. In my project settings I added Thanksgiving and Christmas holidays to "Non-working days" and you can see these shaded.
My task, "Receive F modules" should take 4 weeks starting on 11/21. The vendor I order these parts from is not affected by Thanksgiving or Christmas. Therefore, the finish date should be 12/18.
On my Gantt chart, however, you can see that "Receive F Modules" is affected by my scheduled non-working days.
The work around that I discovered is that I can manually figure out my 4 week lead time (12/18 delivery date) and instead of entering a duration, I select 12/18 as a finish date.
这是最好的方法吗?我做贝蒂吗r job in describing my problem?
-
There is a help article published that may solve this - basically uses elapsed time rather than something that checks holiday and non-working time. Here is link to article:
https://community.smartsheet.com/discussion/17951/independent-work-days-for-tasks-or-resources
Categories
This method does produce separate reports:<\/p>
The Project Plan report will include this filter: \"Sheet Type\" is one of \"Project Plan\" -- this filter will exclude rows coming from the RAID Log (and all other types of sheets) because those other sheets will have a value in their \"Sheet Type\" column that is not \"Project Plan.\" <\/p>
The RAID Log report will include this filter: \"Sheet Type\" is one of \"RAID Log\" -- this filter will exclude rows coming from the Project Plan (and all other types of sheets) because those other sheets will have a value in their \"Sheet Type\" column that is not \"RAID Log.\" <\/p>
Thus, each report will include a filter rule specifying that only rows with its own sheet type can be included.<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":321,"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":265,"urlcode":"Reports","name":"Reports"}]},{"discussionID":108417,"type":"question","name":"How do i set up a conditional format, when i want more than one person in the assigned to column","excerpt":"I have each assigned to person with conditional format with a color to let them know what they are assigned to work, but what if i need two or more associates to work that particular assignment, how do i set up conditional formatting for that, or would that be a formula?","snippet":"I have each assigned to person with conditional format with a color to let them know what they are assigned to work, but what if i need two or more associates to work that…","categoryID":321,"dateInserted":"2023-08-02T14:26:40+00:00","dateUpdated":null,"dateLastComment":"2023-08-02T15:27:36+00:00","insertUserID":159629,"insertUser":{"userID":159629,"name":"Genesia","url":"https:\/\/community.smartsheet.com\/profile\/Genesia","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-08-02T20:20:14+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"updateUserID":null,"lastUserID":159629,"lastUser":{"userID":159629,"name":"Genesia","url":"https:\/\/community.smartsheet.com\/profile\/Genesia","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-08-02T20:20:14+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":2,"countViews":25,"score":null,"hot":3381977656,"url":"https:\/\/community.smartsheet.com\/discussion\/108417\/how-do-i-set-up-a-conditional-format-when-i-want-more-than-one-person-in-the-assigned-to-column","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/108417\/how-do-i-set-up-a-conditional-format-when-i-want-more-than-one-person-in-the-assigned-to-column","format":"Rich","tagIDs":[245,254,334,437],"lastPost":{"discussionID":108417,"commentID":388509,"name":"Re: How do i set up a conditional format, when i want more than one person in the assigned to column","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/388509#Comment_388509","dateInserted":"2023-08-02T15:27:36+00:00","insertUserID":159629,"insertUser":{"userID":159629,"name":"Genesia","url":"https:\/\/community.smartsheet.com\/profile\/Genesia","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-08-02T20:20:14+00:00","banned":0,"punished":0,"private":false,"label":"✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Get Help","url":"https:\/\/community.smartsheet.com\/categories\/get-help"},{"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B"}],"groupID":null,"statusID":3,"image":{"url":"https:\/\/us.v-cdn.net\/6031209\/uploads\/9VLKF1G9AO1Q\/image.png","urlSrcSet":{"10":"","300":"","800":"","1200":"","1600":""},"alt":"image.png"},"attributes":{"question":{"status":"accepted","dateAccepted":"2023-08-03T09:17:11+00:00","dateAnswered":"2023-08-02T14:42:44+00:00","acceptedAnswers":[{"commentID":388483,"body":"