Has anyone had the situation where you have added tasks to a plan, Saved, and then come back later to find that the new tasks are not on the plan? I manage several projects and this has been happening for a couple of days now on one of my projects.
Do you have a filter applied to the sheet and your tasks are not meeting the filter criteria? This means you could save them, they would display (we don't filter them away unless the filter is reapplied), but upon viewing the sheet with the same filter they would be filtered out.