Locking Rows in Dynamic View

Andrea Mayer
Andrea Mayer ✭✭✭✭✭

Hello,

I currently have a report in Dynamic View that is used by project leaders to update monthly financial data. I understand how to set specific fields to read-only but not entire rows. In the screenshot below, I would like to lock the "Target" ROW (highlights in blue) but would still like the project leaders to be able to make updates in for each month in the "Actuals/Forecast" row. Is this possible? If so, how?

image.png

Thanks,

Andrea

Best Answers

Answers

  • Paul Newcome
    Paul Newcome ✭✭✭✭✭✭

    Have you tried locking the row in the actual sheet?

  • Andrea Mayer
    Andrea Mayer ✭✭✭✭✭

    Hi Paul - yes, it is locked in the sheet but that doesn't pull into Dynamic View.

  • Andrea Mayer
    Andrea Mayer ✭✭✭✭✭
    Answer ✓

    嗨——我found a workaround and no longer need an answer to this. Thank you!

  • Paul Newcome
    Paul Newcome ✭✭✭✭✭✭

    Are you able to post the workaround so that others searching for a similar solution can know that one may be found here?

  • Paul Newcome
    Paul Newcome ✭✭✭✭✭✭

    When going through the details panel, you can set specific columns to read only, and you can also leverage conditional logic within the details panel.

  • Andrea Mayer
    Andrea Mayer ✭✭✭✭✭

    Hi Paul,

    I do not want to lock entire columns, because I still need specific fields within those columns to be editable. I have not found a way for the conditional logic to help with this scenario.

    The workaround I have found is a little clunky but works for what I need. A field in Dynamic View is locked if it is a formula in the source sheet. For each of the fields that I need locked, I have manually entered and "=" in front of each figure. This still shows the same figure in the source sheet and ensures users cannot edit those fields in Dynamic View. This also ensures the other fields within that column are also still editable.

    Thanks,

    Andrea

  • Paul Newcome
    Paul Newcome ✭✭✭✭✭✭
    Answer ✓

    With conditional logic in Dynamic view, it would not be the entire column that is locked. Only for rows that meet the criteria. It would be on a row by row basis depending on the data in the other cells within that row that determines whether that column in that row can be edited or not.

  • Andrea Mayer
    Andrea Mayer ✭✭✭✭✭

    I'll test this out. Thanks Paul!

  • Paul Newcome
    Paul Newcome ✭✭✭✭✭✭

    Happy to help.


    I personally have leveraged this so that people could see upcoming due dates but could only update the "actual" date for the current stage. So if we have stages 1 - 5, you can use the conditional logic to say that if the current stage is 1, show "Stage 1 Actual" as editable, but then show stages 2 - 5 "due" as read only. Then the next one is if the current stage is stage 2, then show "Stage 2 Actual" as editable and stages 3 - 5 "due" as read only. This is will work on a row by row basis and basically limit which columns can and cannot be edited based on the current stage.

Hi @Matthew LeMasonry<\/a> <\/p>

No, it currently isn't possible to share the Data Shuttle workflow configuration with another account. The set-up for that workflow is associated with one account. (Please let our Product team know of your feature request by filling in this form, here!)<\/a><\/p>

That said, many team members will be able to trigger<\/em> that workflow, depending on what that trigger is. For example, if the workflow is based on an attachment, any user can upload the attachment for the workflow. Does that make sense?<\/p>

If you are looking to transfer workflows because a user has left the organization, you could potentially update the Primary email address associated with the account that owns the configurations. This will allow you to gain access to the Data Shuttle workflows from the new email. Keep in mind this would need to be an email that does not currently have a Smartsheet account. See: Admin Center: Add, Edit, and Delete Individual Users with User Management<\/a><\/p>

Cheers,<\/p>

Genevieve<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":343,"name":"Add Ons and Integrations","url":"https:\/\/community.smartsheet.com\/categories\/apps-and-integrations","allowedDiscussionTypes":["discussion","question"]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":2},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[]},{"discussionID":107864,"type":"question","name":"Anyone else having issues with Calendar App not Downloading PDF of entire calendar?","excerpt":"I have been on the phone with Smartsheet support this week but we have been unable to figure out what could be causing this issue. I am finding that the Calendar app is only Downloading one page of a PDF, cutting off any information that would be on the subsequent pages. Example below You can see the bottom four lines,…","snippet":"I have been on the phone with Smartsheet support this week but we have been unable to figure out what could be causing this issue. I am finding that the Calendar app is only…","categoryID":343,"dateInserted":"2023-07-20T16:17:45+00:00","dateUpdated":null,"dateLastComment":"2023-07-25T16:28:06+00:00","insertUserID":156581,"insertUser":{"userID":156581,"name":"Macorne","url":"https:\/\/community.smartsheet.com\/profile\/Macorne","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-27T17:22:01+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭"},"updateUserID":null,"lastUserID":156581,"lastUser":{"userID":156581,"name":"Macorne","url":"https:\/\/community.smartsheet.com\/profile\/Macorne","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-27T17:22:01+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":2,"countViews":43,"score":null,"hot":3380173551,"url":"https:\/\/community.smartsheet.com\/discussion\/107864\/anyone-else-having-issues-with-calendar-app-not-downloading-pdf-of-entire-calendar","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/107864\/anyone-else-having-issues-with-calendar-app-not-downloading-pdf-of-entire-calendar","format":"Rich","tagIDs":[449],"lastPost":{"discussionID":107864,"commentID":386931,"name":"Re: Anyone else having issues with Calendar App not Downloading PDF of entire calendar?","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/386931#Comment_386931","dateInserted":"2023-07-25T16:28:06+00:00","insertUserID":156581,"insertUser":{"userID":156581,"name":"Macorne","url":"https:\/\/community.smartsheet.com\/profile\/Macorne","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-27T17:22:01+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Get Help","url":"https:\/\/community.smartsheet.com\/categories\/get-help"},{"name":"Add Ons and Integrations","url":"https:\/\/community.smartsheet.com\/categories\/apps-and-integrations"}],"groupID":null,"statusID":3,"image":{"url":"https:\/\/us.v-cdn.net\/6031209\/uploads\/JTO6PBQV26S0\/pdf-cutoff-png.png","urlSrcSet":{"10":"","300":"","800":"","1200":"","1600":""},"alt":"PDF cutoff.PNG"},"attributes":{"question":{"status":"accepted","dateAccepted":"2023-07-25T16:27:54+00:00","dateAnswered":"2023-07-25T12:38:16+00:00","acceptedAnswers":[{"commentID":386813,"body":"

Hey @Macorne<\/a> <\/p>

I checked in with our Support team and they confirmed that two other users had reported a similar behaviour as well. Thank you for your patience and persistence as we looked into this!<\/p>

We've since had confirmation that there has been a fix in the Print behaviour for the Calendar app as of this weekend. Please try again and let us know if this has now been resolved for you. <\/p>

Cheers,<\/p>

Genevieve<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":343,"name":"Add Ons and Integrations","url":"https:\/\/community.smartsheet.com\/categories\/apps-and-integrations","allowedDiscussionTypes":["discussion","question"]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":449,"urlcode":"calendar-app","name":"Calendar App"}]},{"discussionID":72863,"type":"question","name":"Document Builder - date format?","excerpt":"I am trying to generate certificates of completion with document builder and include the date of conferral. No matter how I enter the date into a date field (my preference is \"Friday, January 1, 2021\" as the format), it always enters in the 1\/1\/21 format. Any ideas for getting document builder to fill it correctly?","snippet":"I am trying to generate certificates of completion with document builder and include the date of conferral. No matter how I enter the date into a date field (my preference is…","categoryID":343,"dateInserted":"2020-11-04T23:06:36+00:00","dateUpdated":"2022-06-14T14:37:26+00:00","dateLastComment":"2023-07-21T23:09:55+00:00","insertUserID":128195,"insertUser":{"userID":128195,"name":"Robin Sugiura","url":"https:\/\/community.smartsheet.com\/profile\/Robin%20Sugiura","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-07T19:16:47+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭"},"updateUserID":91566,"lastUserID":150391,"lastUser":{"userID":150391,"name":"Rebecca Ortinez","url":"https:\/\/community.smartsheet.com\/profile\/Rebecca%20Ortinez","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-26T18:48:36+00:00","banned":0,"punished":0,"private":false,"label":"✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":14,"countViews":785,"score":1,"hot":3294520891,"url":"https:\/\/community.smartsheet.com\/discussion\/72863\/document-builder-date-format","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/72863\/document-builder-date-format","format":"Rich","lastPost":{"discussionID":72863,"commentID":386528,"name":"Re: Document Builder - date format?","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/386528#Comment_386528","dateInserted":"2023-07-21T23:09:55+00:00","insertUserID":150391,"insertUser":{"userID":150391,"name":"Rebecca Ortinez","url":"https:\/\/community.smartsheet.com\/profile\/Rebecca%20Ortinez","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-07-26T18:48:36+00:00","banned":0,"punished":0,"private":false,"label":"✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Get Help","url":"https:\/\/community.smartsheet.com\/categories\/get-help"},{"name":"Add Ons and Integrations","url":"https:\/\/community.smartsheet.com\/categories\/apps-and-integrations"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2020-11-05T09:58:05+00:00","dateAnswered":"2020-11-04T23:19:01+00:00","acceptedAnswers":[{"commentID":267977,"body":"

I figured out a workaround -- if the date is entered in long form in a text column instead of a date column, it populates as entered. <\/p>

Don't know if there is another way to affect the formatting if populating from a date column.<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":343,"name":"Add Ons and Integrations","url":"https:\/\/community.smartsheet.com\/categories\/apps-and-integrations","allowedDiscussionTypes":["discussion","question"]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":1},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[]}],"initialPaging":{"nextURL":"https:\/\/community.smartsheet.com\/api\/v2\/discussions?page=2&categoryID=343&includeChildCategories=1&type%5B0%5D=Question&excludeHiddenCategories=1&sort=-dateLastComment&limit=3&expand%5B0%5D=all&expand%5B1%5D=-body&expand%5B2%5D=insertUser&expand%5B3%5D=lastUser&status=accepted","prevURL":null,"currentPage":1,"total":626,"limit":3},"title":"Trending Posts","subtitle":null,"description":null,"noCheckboxes":true,"containerOptions":[],"discussionOptions":[]}">

Trending Posts