Contingency duration based on predecessors
I was wondering if it is possible to create a task whose duration is determined by two predecessors, onefrom backward planningand onefrom forward constraints. I would like to use this, among others, to showdynamic contingency periodsin my project.
Let's take the simplest example, a project with the following three lines:
1. Milestone 1 at the start of the project, say, 8/29/16.
2. Milestone 2 at the required completion date of the project, say, 9/30/16.
3. A task, "Contingency," with a non-zero duration. The end date of this task should be determined backwards by the predecessor on Line 2, while the start of the task should be determined forward by the predecessor on Line 1.
That's not what I want. Is there a way of getting this done?
Thanks
Comments
-
Kennedy Stomps Employee
Hi Thomas-- We don't currently support constraints in Smartsheet, so as far as I'm aware, this wouldn't currently be possible. This is definitely something our team can consider implementing in a future release and I'll pass along your input!
-
Thank you. Yes, this would be important; other project planning tools have it and I like it.
-
A workaround for the dynamic duration of the item task.
As we cannot out of the box get a dynamic calculation out of the dependencies.
Workaround : --> create two child items (0 duration milestone) : ==> the parent will get the duration between the milestones.
Master task
- one item with the start dependency
- one item with the stop dependency
==> duration is then automatically calculated.
Categories
You need to remove the closing parenthesis from before the comma.<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":343,"name":"Add Ons and Integrations","url":"https:\/\/community.smartsheet.com\/categories\/apps-and-integrations","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[]},{"discussionID":107143,"type":"question","name":"How can I get (on a separate metric sheet) the average SLA time within a given month?","excerpt":"I am trying to create a metric sheet to document how long response and acknowledgement times are taking per month for record keeping. I have a sheet that has an acknowledgement SLA column and a \"date of request\" (auto column for when the submission was created), and I'm looking to record the average for each month on a…","snippet":"I am trying to create a metric sheet to document how long response and acknowledgement times are taking per month for record keeping. I have a sheet that has an acknowledgement…","categoryID":322,"dateInserted":"2023-06-30T15:31:46+00:00","dateUpdated":null,"dateLastComment":"2023-06-30T17:30:08+00:00","insertUserID":159225,"insertUser":{"userID":159225,"name":"laney_white","url":"https:\/\/community.smartsheet.com\/profile\/laney_white","photoUrl":"https:\/\/aws.smartsheet.com\/storageProxy\/image\/images\/u!1!5FvXObtmaHw!CVFXQvc68Xo!anynrNoWe-v","dateLastActive":"2023-06-30T17:19:19+00:00","banned":0,"punished":0,"private":false,"label":"✭✭"},"updateUserID":null,"lastUserID":161714,"lastUser":{"userID":161714,"name":"Carson Penticuff","url":"https:\/\/community.smartsheet.com\/profile\/Carson%20Penticuff","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/B0Q390EZX8XK\/nBGT0U1689CN6.jpg","dateLastActive":"2023-06-30T19:17:25+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":3,"countViews":21,"score":null,"hot":3376287114,"url":"https:\/\/community.smartsheet.com\/discussion\/107143\/how-can-i-get-on-a-separate-metric-sheet-the-average-sla-time-within-a-given-month","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/107143\/how-can-i-get-on-a-separate-metric-sheet-the-average-sla-time-within-a-given-month","format":"Rich","tagIDs":[254],"lastPost":{"discussionID":107143,"commentID":383369,"name":"Re: How can I get (on a separate metric sheet) the average SLA time within a given month?","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/383369#Comment_383369","dateInserted":"2023-06-30T17:30:08+00:00","insertUserID":161714,"insertUser":{"userID":161714,"name":"Carson Penticuff","url":"https:\/\/community.smartsheet.com\/profile\/Carson%20Penticuff","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/B0Q390EZX8XK\/nBGT0U1689CN6.jpg","dateLastActive":"2023-06-30T19:17:25+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions"}],"groupID":null,"statusID":3,"image":{"url":"https:\/\/us.v-cdn.net\/6031209\/uploads\/ZXS917R2FJKC\/master-sheet-png.png","urlSrcSet":{"10":"","300":"","800":"","1200":"","1600":""},"alt":"master sheet.PNG"},"attributes":{"question":{"status":"accepted","dateAccepted":"2023-06-30T17:19:35+00:00","dateAnswered":"2023-06-30T15:50:27+00:00","acceptedAnswers":[{"commentID":383345,"body":"
If I understand correctly, this may help.<\/p>
=AVERAGEIF({date of request}, MONTH(@cell) = 2, {Ack SLA})<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":322,"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":254,"urlcode":"Formulas","name":"Formulas"}]}],"initialPaging":{"nextURL":"https:\/\/community.smartsheet.com\/api\/v2\/discussions?page=2&includeChildCategories=1&type%5B0%5D=Question&excludeHiddenCategories=1&siteSectionID=0&sort=-hot&limit=3&expand%5B0%5D=all&expand%5B1%5D=-body&expand%5B2%5D=insertUser&expand%5B3%5D=lastUser&status=accepted","prevURL":null,"currentPage":1,"total":10000,"limit":3},"title":"Trending Posts","subtitle":null,"description":null,"noCheckboxes":true,"containerOptions":[],"discussionOptions":[]}">