Overriding Non-Working Days
Most of our projects include M-F working dates, however at the end of each project there is often a conference or event which may take place over a weekend or other non-working day. I'd love to be able to override and enter tasks on weekends for these instances without turning the entire project into a 7-day work week project and accidentally having other tasks "pushed" onto a weekend by mistake. Is there a way to override?
Comments
-
Victor van R ✭✭
I think the only way is to make the default a 7 days working week and make the 'normal' weekends exception.
-
Do you mean set the working week to 7 days but make all weekends (except for the weekend of the event) a non-working/holiday/vacation status?
That might work. Thanks!
-
Victor van R ✭✭
Yes, that is what I mean. It is a bit basic workaround but it works.
-
If its only only a weekend here and there, you could do the following:
-Create a new task (row) for Sat and Sun (each row only scheduled on one day)
-Create a row above the two weekend rows.
-Indent the two weekend rows under the new row
Now you can collapse the two weekend rows under the parent row to give the impression of a single row but still have your weekend task.
-
Crissy Nolen ✭✭
- Elapsed time (lead with an e to indicate duration in elapsed time e.g. e3d, e5h, e3.5d, etc). A task with a duration in elapsed time ignores non-working time. The task will start and end in the amount of time specified regardless of working day length and non-working days in the sheet.
-
Adding the Sat and Sun rows indented gives the impression in the gantt view but the days total is only 1d for a Fri-Sun range instead of 3d.
-
Thanks "Crissy Nolen"
I'd tried it and it is working fine
-
Brilliant, thank you!
-
Thanks for solving this for me -- just the guidance I needed!
-
Crissy, hello.
I have a date and duration calculating problem where a task of 6 days duration is behaving in an odd manner when I try to use your prefix 'e' solution to "override" Sat and Sun as non-work days within Project Settings.
Grid and Calendar Views both show 7 days Duration instead of the specified/required 6 days, and Gantt View shows just 5 days.
Any thoughts as to what I may be doing wrong?
Any help appreciated!
-
Zachw ✭✭✭
Thank you for this, works perfectly
Categories
=(NETDAYS([Requested Start Date]@row, DATE(2022, 12, 1)<\/strong>) \/ 365) * 12<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":322,"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":254,"urlcode":"Formulas","name":"Formulas"}]},{"discussionID":107082,"type":"question","name":"Automatic Update of Dropdown List?","excerpt":"I saw several discussions on this and I'm wondering if there is a formula or an easy way without a 3rd party to automatically update a dropdown list based on a cell in one sheet? I can create a helper sheet if that would help. Any ideas? I don't believe I have the premium Smartsheets plan. Thank you! Lori","snippet":"I saw several discussions on this and I'm wondering if there is a formula or an easy way without a 3rd party to automatically update a dropdown list based on a cell in one sheet?…","categoryID":322,"dateInserted":"2023-06-29T14:16:13+00:00","dateUpdated":null,"dateLastComment":"2023-06-29T18:02:59+00:00","insertUserID":162337,"insertUser":{"userID":162337,"name":"maineL","title":"Admin. & Course Coordinator","url":"https:\/\/community.smartsheet.com\/profile\/maineL","photoUrl":"https:\/\/aws.smartsheet.com\/storageProxy\/image\/images\/u!1!plNXqQdBs_o!2kvQ_7y42f4!PTHvB33mICN","dateLastActive":"2023-06-29T18:08:11+00:00","banned":0,"punished":0,"private":false,"label":"✭✭"},"updateUserID":null,"lastUserID":8888,"lastUser":{"userID":8888,"name":"Andrée Starå","title":"Smartsheet Expert Consultant & Partner | Workflow Consultant \/ CEO @ WORK BOLD","url":"https:\/\/community.smartsheet.com\/profile\/Andr%C3%A9e%20Star%C3%A5","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/0PAU3GBYQLBT\/nXWM7QXGD6464.jpg","dateLastActive":"2023-06-29T18:24:32+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":11,"countViews":47,"score":null,"hot":3376116552,"url":"https:\/\/community.smartsheet.com\/discussion\/107082\/automatic-update-of-dropdown-list","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/107082\/automatic-update-of-dropdown-list","format":"Rich","lastPost":{"discussionID":107082,"commentID":383175,"name":"Re: Automatic Update of Dropdown List?","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/383175#Comment_383175","dateInserted":"2023-06-29T18:02:59+00:00","insertUserID":8888,"insertUser":{"userID":8888,"name":"Andrée Starå","title":"Smartsheet Expert Consultant & Partner | Workflow Consultant \/ CEO @ WORK BOLD","url":"https:\/\/community.smartsheet.com\/profile\/Andr%C3%A9e%20Star%C3%A5","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/0PAU3GBYQLBT\/nXWM7QXGD6464.jpg","dateLastActive":"2023-06-29T18:24:32+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2023-06-29T14:52:00+00:00","dateAnswered":"2023-06-29T14:50:26+00:00","acceptedAnswers":[{"commentID":383100,"body":"