Most of our projects include M-F working dates, however at the end of each project there is often a conference or event which may take place over a weekend or other non-working day. I'd love to be able to override and enter tasks on weekends for these instances without turning the entire project into a 7-day work week project and accidentally having other tasks "pushed" onto a weekend by mistake. Is there a way to override?
Elapsed time (lead with an e to indicate duration in elapsed time e.g. e3d, e5h, e3.5d, etc). A task with a duration in elapsed time ignores non-working time. The task will start and end in the amount of time specified regardless of working day length and non-working days in the sheet.
I have a date and duration calculating problem where a task of 6 days duration is behaving in an odd manner when I try to use your prefix 'e' solution to "override" Sat and Sun as non-work days within Project Settings.
Grid and Calendar Views both show 7 days Duration instead of the specified/required 6 days, and Gantt View shows just 5 days.
\"//www.santa-greenland.com/community/discussion/comment/\", [Project Lead]:[Project…","snippet":"This formula is currently working, and it is returning how many items are reviewed for each \"Project Lead\". The first part of the formula is basically saying that we would count…","categoryID":322,"dateInserted":"2023-06-29T22:39:31+00:00","dateUpdated":null,"dateLastComment":"2023-06-30T02:51:05+00:00","insertUserID":157974,"insertUser":{"userID":157974,"name":"Filippo","url":"https:\/\/community.smartsheet.com\/profile\/Filippo","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-06-30T03:08:32+00:00","banned":0,"punished":0,"private":false,"label":"✭✭"},"updateUserID":null,"lastUserID":157974,"lastUser":{"userID":157974,"name":"Filippo","url":"https:\/\/community.smartsheet.com\/profile\/Filippo","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-06-30T03:08:32+00:00","banned":0,"punished":0,"private":false,"label":"✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":2,"countViews":20,"score":null,"hot":3376173036,"url":"https:\/\/community.smartsheet.com\/discussion\/107113\/how-to-return-a-blank-if-we-have-a-blank-cell-using-a-countifs-formula","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/107113\/how-to-return-a-blank-if-we-have-a-blank-cell-using-a-countifs-formula","format":"Rich","lastPost":{"discussionID":107113,"commentID":383252,"name":"Re: How to return a BLANK if we have a BLANK cell using a COUNTIFS formula","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/383252#Comment_383252","dateInserted":"2023-06-30T02:51:05+00:00","insertUserID":157974,"insertUser":{"userID":157974,"name":"Filippo","url":"https:\/\/community.smartsheet.com\/profile\/Filippo","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-06-30T03:08:32+00:00","banned":0,"punished":0,"private":false,"label":"✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2023-06-30T02:51:53+00:00","dateAnswered":"2023-06-29T22:55:01+00:00","acceptedAnswers":[{"commentID":383233,"body":"