- Floating dependency start dates
I have two dates: A and B. B's start is dependent on A's completion. If everything goes as planned, A will finish on 2/27 and B will start on 4/1. B's start date is constant unless A's finish is delayed beyond the planned start. For example, if A is delayed until 3/15, B will still start on 4/1; but if A is delayed until…
- Complex Formula Help Needed
On a Gantt chart, I've added a column % Progress Expected and I have it calculating % progress expected per day for each line item, based on the duration; see formula below. =(TODAY() - Start@row) * ([ADMIN: % EXPECTED DAILY PROGRESS]@row) * 1.1 The problem I'm trying to solve for is I need it to show 0% progress expected…
- Gantt Chart - Percentage Complete
Hi, I'm new in Smartsheet coming from the MS Project world. I'm trying to include the % of task completion in a gantt chart. I'm filling in the % complete column but nothing appears on the gannt chart (contrary to what is described in…
- Complex nested IF, AND with traffic light symbols
Hi All, I'm working on automating a symbol highlighter to indicate project progress as well as alerting if key milestones are being compromised. The formula below is structured based on the following columns: * Finish: The Activity completion date * Start: The activity start date * Date: A column containing fixed dates to…
- I need to use an IF / THEN formula to compare a cell from one column to a cell in another column
I could really use some help! Thank you in advance! My STATUS column has the following colored options available per cell: Red, Yellow, Green and Blue. I am looking to use the following IF / THEN statements: 1. In STATUS, if the DELIVERY DATE is within SEVEN (7) DAYS of the START DATE, the LIGHT is RED. Can the DELIVERY…
- Time Tracking
I'm new to SmartsSheet and don't see an obvious way to track time, and have it recorded against a task Personally not too fond of % complete - to often I've seen people say/think (legit or not) that they're 90% done, and the last 10% takes as long as the first 90% (or, unfortunately, more) People often think they're almost…
- Is there a formula/function to help count number of children assigned to specific parent tasks?
Hi all, I'm trying to put together a table that lists the number of sub-tasks (children) in each respective Workstream (parent) of a specific Project Plan, and also breaks these down into their respective Health Status (Green, Yellow, Red). I am aware that I can apply a "COUNTIF" formula and set the range to encompass the…
- Start and end date line chart
嗨,团队,谁能help me how can I create a line chart based on below information. I
- Dependency Logic based on one or the other predecessor tasks
Is is possible to create schedule logic where a dependent task is dependent on one of two predecessors (either or not both)? For Example: I am trying to build out a schedule template for if a permit is required vs not for a specific project. IF a permit is required then the rest of the schedule should be based on the…
- Gnatt chart Bar formatting - grid missing
H Folks, For some reason I have areas in my smartsheet plan that have grid missing, some are ok. Does anyone have an idea how I can correct this and add the gridelines back please. thanks Mark,