I Found The Issue with The Parenthesis: Updated Formula: =IF(NOT(ISBLANK([email protected])), ($[Project Budget]$1 -[email protected]) / ($[Project Budget]$1 -[email protected]))
-
Excellent, Thanks @Jeff Reisman
-
=IF(NOT(ISBLANK([TEAC (Days)]@row)), $[Start Date]$1 + [TEAC (Days)]5)
-
Disregard Smartsheet Community. I Figured it Out. =IF(NOT(ISBLANK([TEAC (Days)]@row)), $[Start Date]$1 + [TEAC (Days)]5)
-
Yes, That Worked! I See The IF(NOT(ISBLANK([email protected])只是开始。谢谢
-
Please Add Full @mention Functionality to WorkApps. I Have to Type The Entire Email Address to Use @mention Functionality.
-
Smartsheet Community: I Created a Helper Column to Only Populate the Risk Score when The Status is Open or in Potential Status. Here is The Formula: =AVGW([Risk Score Helper]:[Risk Score Helper], [Schedule Impact]:[Schedule Impact])
-
That Worked! I had the d on the Inside of the Parenthesis. Thanks Jeff & Toufong
-
Excellent! That worked Perfectly. Thanks
-
Almost, but the Tolerance is Up to 4 Day Behind Plan is Yellow, and anything Greater than 4 Days behind Plan should turn Red. Plan = Actual is Green. The See Screen Shot Below is 2 Days Behind Plan but The Milestone Health does not Turn Yellow: