Comments
-
Hi @Genevieve P. I use a similar formula to the one mentioned above to determine the project's health using the baseline finish, the actual end date, and the completion percentage. Could you kindly elaborate on the Schedule Delta (Working Days) and Schedule Delta (%) formulas? I'm intrigued to know how they affect projects…
-
Hi @Genevieve P. I have a similar request: When adding a new task to a project plan, the baseline start and finish are not automatically populated. As a result, I must reset the baseline each time, and even though I can copy and adjust the current sheet's dates to match the baseline dates, this takes time because I need to…
-
Hi @Genevieve P. Good Day! May i please know the latest update for adding parent and child tasks via form submission.? Thanks!