  • 地狱o Hamza, I just tested this and still receive the same result as my original post. I am not able to preview PDF attachments in a report while using the desktop application. My only option is to download them. -Terry
  • 地狱o Hamza, I just tested this and still receive the same result as my original post. I am not able to preview PDF attachments in a report while using the desktop application. My only option is to download them. -Terry
  • I would like to voice my displeasure with the removal of the delete user option. This does not help me as a System Admin. I wont go on a long rant, my reasons are the same or similar to every commenter who has posted before me. Let this be my vote to reinstate the delete user option. -Terry
  • Ignore my question, in my ignorance I did not actually test to see if it would work before asking my question. It eliminates the cross sheet references and only returns the value from the sheet.
  • 地狱o Andree, Above is a screenshot of what an order generally looks like for us. The assigned to column from top to bottom follows the order of real life milestones for work centers. All this gets entered in by a production planner and then they hand out paperwork and the assigned work centers accomplish a task and fill…
  • Appreciate the help Paul, because of your advice I have added a work_days column. Formula>>> =IFERROR(ROUND([Projected Hours]/ 8, 0), "") End Date is then using the WORKDAY function you mentioned to return my desired date. Exactly what I was looking to do, thank you Paul.
  • Thank you for your suggestion Paul. Workday functions will not work as I am not looking to get a number of days between two date cells. I need an End Date cell to populate based on 1 date and an hours cell. I would like the End Date that is populated to take both of these columns into account and skip Saturday and Sunday.…
  • I actually did this morning on your recommendation after the column had moved again. I saw that one of my users had a 'Column Reordered' event in the log. However this particular user does not have the correct permissions in the sheet to move columns so I'm not sure how this is possible. I just double checked his…
  • I submitted a ticket with Smart Sheet support on Tuesday and here I am on Thursday with still no response. The columns remained stable for 2 days and then i logged in after my production meeting this morning and my column had moved again to the end of the sheet. Very disappointed in the lack of response from the support…