Fantastic. Thanks, Shaine. Will submit a feature request and dig into the article. Thanks for taking time to respond. Tim (Australia)
-
Hi, Shaine. Appreciate the response. What I failed to ask was, is there a method of pushing a dependent task forward to the Saturday following - automatically so that regardless of the day of the week a predecessor finishes, the dependent task will always start on the following Saturday - without me manually changing start…
-
Crissy, hello. I have a date and duration calculating problem where a task of 6 days duration is behaving in an odd manner when I try to use your prefix 'e' solution to "override" Sat and Sun as non-work days within Project Settings. Grid and Calendar Views both show 7 days Duration instead of the specified/required 6…